Project Size: 72,000 m²
Value: $ 6.4 Million
Builder: Leighton Contractors
Program: Start Date: August 2008
Handover Date: October 2009

Application
RAF 01 - CF Bare Panel
FAF 02 - CF HPL Rigid Grid system
FFH 150mm

access floor at westpac head office sydney

Provide an access floor for the purpose of distributing cables/ data and power throughout the building without the need for cable trays.

Provide computer room floors to several IT and Comms rooms throughout the building.

Scope of work
Supply and installation of stringer less ASP CF system to general office area with a FFH of 150mm.

Installation of heavy grade data/comms room access floor for smaller communication room throughout the building.

westpac access floor



ASP Access Floors Pty Ltd Profile

02 9620 9915

32 Prime Drive, Seven Hills, NSW, 2147.

Video

ASP Access Floors Pty Ltd Profile

02 9620 9915

ENQUIRE HERE

ENQUIRE NOW

Video






Related News Articles