Job Name
Kurnell Desalination Plant
Job Address
Sir Joseph Banks Drive, Kurnell
Builder/Developer
Bluewater Joint Venture
Equipment hired
305 cranes and 2 drivers
Length of job
2 months work last year from September, continuous work from February 2009, additional night shift from September 2009
Scope of job
Installation of secondary steel components in the main filtration (R/O) building. Also installing fibreglass and stainless steel piping along with various valves and other components.
Hirer comment/s
Leigh Moles from Bluewater "The Supermini Crawler MC-305 is needed because of the tight areas and spaces to be worked in. The engineering restrictions of the site have also meant that larger cranes are unable to operate in this particular building. The Supermini Crawler has also enabled us to stay on track with our construction forecast. We have found Preston to be highly competent and professional, both in site personnel and admin staff".
Preston Comment
"Our Maeda 305 mini crawler cranes were a perfect choice for the job as the site was very constrictive and the concrete slab specifications would not allow larger plant to operate on it."