How to Build with ZEGO Building Systems in Six Easy Steps![]()
Once the slab is completed, measure the outside, dividing walls and doorways. Then, mark out with a coloured chalk line on the floor. Place a 110mm wide damp proof course (DPC) or liquid membrane on the slab.
Now, fix the Patented Wall Brace Scaffold to the floor using 8mm reusable masonry anchors. Set the Wall Brace plumb, using a spirit level and the adjustable in-built screw tensioner.
Use a dumpy or laser level to mark a datum level on all Wall Brace Support Scaffolds.
|